09:42 AM EST - Endeavour Silver Corp. : Announced the successful fabrication and installation of its primary ball mill trunnion at the Guanaceví mine. Guanaceví processing resumed to full capacity this week after the trunnion failure in August. After a 15-week period of operating at a reduced capacity averaging 620 tonnes per day (tpd), the newly fabricated trunnion was installed on November 30 with alignment testing occurring over the ensuing two weeks, restoring the plant to its designed capacity of 1,200 tpd. The total cost of fabrication and installation was just over US$400,000. Endeavour Silver Corp.
shares T.EDR are trading unchanged at $5.48.